Findings · Transmission · Part 2, How the assets were obtained
Where transmission auctions were open, Adani won by fractions of a percent
For the first phase of the Khavda transmission lines, 7; Adani won at Rs 1,000.33 million a year against Power Grid's Rs 1,002.84 million. At Karur, Adani won at Rs 183.54 million a year against Sterlite's Rs 184.01 million.
| Date | What the record shows | Document |
|---|---|---|
| 2017 | MERC Case 140 of 2017: assignment of distribution licence to subsidiary as step in sale | Executive Summary, Case No. 140 of 2017, paras 1-7 |
| 2017-12-21 | RInfra-Adani Transmission definitive agreement for Mumbai integrated power business 18800 Rs crore total consideration (company estimate) | RInfra media release enclosed with letter to BSE/NSE, 28.06.2018, media release para 3 |
| 2018-06-28 | MERC approves sale of RInfra Mumbai business to Adani Transmission | RInfra media release: MERC approves sale (letter to BSE/NSE), media release paras 1-2 |
| 2021-10-21 | Khavda 3 GW Phase-I TBCB: responses to RfP 7 RfP responses (6 qualified; 4 in e-reverse auction) | Order in Petition No. 101/AT/2022 (Khavda-Bhuj Transmission Ltd), paras 14-17 |
| 2021-12-09 | Karur/Tiruppur 1,000 MW TBCB: Adani L-1 183.54 Rs million per annum levelised charges | Order in Petition No. 103/AT/2022 (17.05.2022), paras 13, 19-21 |
| 2021-12-14 | Khavda 3 GW Phase-I: Adani L-1 1000.33 Rs million per annum levelised charges | CERC Order 101/AT/2022 (10.05.2022), para 17 |
| 2023-12-05 | TBCB projects FY2021-23 won by Adani (Ministry of Power annexure) 18.35; 100.03; 213.48; 118.90 Rs crore yearly tariff (Karur; Khavda Ph-I; WR-SR export scheme; Khavda Ph-II Part A) | Annexure: Transmission projects awarded under TBCB, FY2021-FY2023 (reply to RS Unstarred Q 317), Annexure-I rows 7, 8, 23 and Khavda Ph-II Part A |
Not every award in Part 2 was thin. These two were contested to the last rupee, and the paper reports them for that reason.
The documents
From the Central Electricity Regulatory Commission's tariff adoption orders for the two projects (May 2022). Only these two orders were read in full; the others would complete the picture.
Every figure above is in the data tables with its source and page. Read the argument in full in Part 2 of the paper.