Adani and Ambani

Findings · Oil and gas · Part 2, How the assets were obtained

The auditor could not validate Reliance's KG-D6 costs, and later put excess cost recovery at US$ 1,548 million

The Comptroller and Auditor General's 2011 audit found that the whole KG-D6 block had been treated as a discovery area, so none was relinquished; that estimated development spending rose from US$ 2.4 billion to US$ 8.8 billion; and that 10 (8 to Aker Group) high-value contracts went on single financial bids. The 2016 follow-up put excess cost recovery at US$ 1,547.85 million.

KG-D6: the record
DateWhat the record showsDocument
2000-04PSC for KG-DWN-98/3 signed; block awarded under NELP-I
7645 sq km contract area
CAG Report No. 11 of 2016, Chapter XIV, para 14.1.1, PDF p.1 (printed p.103), para 14.1.1
2009-10 to 2012-13CAG: marketing margin collected outside revenue base
261.33 US$ million
Report No. 24 of 2014, Executive Summary, Exec. Summary PDF p.7, Para 2.8.3.1
2011-09-08CAG performance audit of hydrocarbon PSCs tabled (Report No. 19 of 2011-12)Report No. 19 of 2011-12: Performance Audit of Hydrocarbon Production Sharing Contracts, report page (tabling date)
2011-09-08CAG finding: entire contract area allowed as Discovery Area, avoiding 25% relinquishment
7645 sq km retained
Report No. 19 of 2011-12, Executive Summary, Exec. Summary PDF pp.5-6, Para 4.2.1
2011-09-08CAG finding: D1-D3 development plan capex rose from IDP to AIDP
2.4 -> 5.2 (Phase I) + 3.6 (Phase II) US$ billion estimated capex
Report No. 19 of 2011-12, Executive Summary, Exec. Summary PDF p.6, Para 4.3.1
2011-09-08CAG finding: high-value contracts awarded on single financial bids
10 (8 to Aker Group) contracts
Report No. 19 of 2011-12, Executive Summary, Exec. Summary PDF pp.7-8, Paras 4.4, 4.6
2011-09-08CAG finding: Investment Multiple profit-sharing gives contractor incentive to raise or front-load capex
28 -> 85 per cent GoI share of profit petroleum at IM 2.5 (KG-DWN-98/3 bid)
Secondary source
Report No. 19 of 2011-12, Executive Summary, Exec. Summary PDF pp.9-11, Paras 8.1-8.2
2011-11 (initiated)Cost-recovery arbitration (D1/D3 production shortfall)
1.005 (initial disallowance, May 2012 reported); ~247 (GoI claim per RIL, reported); >30 (GoI claim per Reuters) US$ billion / US$ million
Secondary source
reported by Business Standard, Business Today, Reuters (via Outlook Business); primary not found
2012-03CAG: D1-D3 development spending above MC-approved cost; facilities under-utilised
5.76 vs 5.20 approved US$ billion
Report No. 24 of 2014, Executive Summary, Exec. Summary PDF p.4, Paras 2.6.3-2.6.5
2012-12 (report); 2013-06-27 (CCEA)Rangarajan Committee gas price formula; CCEA approval
~8.4 US$/mmBtu (reported projected price from Apr 2014)
Secondary source
reported by Moneylife, Business Standard; PRS summary of Standing Committee report; primary not found
2013-03-31Block expenditure and cost recovery to March 2013
10441.98 spent; 9293.22 cost recovered US$ million
Report No. 24 of 2014, Executive Summary, Exec. Summary p.iii (PDF p.2), para 2.1
2014-11-012014 gas pricing guidelines: KG-D6 D1/D3 price uplift held in gas pool pending cost-recovery arbitration
4.2 US$/mmBtu (price retained; difference to new price credited to GAIL gas pool)
New Domestic Natural Gas Pricing Guidelines, 2014, paras 1-2, 5, 6-7
2014-11-28CAG compliance audit of KG-D6 for 2008-09 to 2011-12 tabled (Report No. 24 of 2014)Report No. 24 of 2014: Compliance Audit on Hydrocarbon Production Sharing Contracts, report page (tabling date)
2014-11-28CAG items recommended for disallowance or recovery (examples)
160.81; 118.99; ~200 (Euro); 17.36; 45; 15 US$ million unless stated
Report No. 24 of 2014, Executive Summary, Exec. Summary PDF pp.3-5, Paras 2.4.2, 2.5.1, 2.7.1.1, 2.7.1.2.1-3
2015-11Gas migration: D&M report on ONGC gas produced through D1-D3
49.32 / 34.71 migrated; of which 85.15 / 73.25 produced via D1-D3 per cent of GIIP (to 31 Mar 2015)
Report No. 11 of 2016, Chapter XIV, para 14.2.2, PDF pp.2-3 (printed pp.104-105), para 14.2.2
2016CAG follow-up audit 2012-14: excess cost recovery
1547.85 US$ million (Rs 9,307.22 crore)
Report No. 11 of 2016, Chapter XIV (MoPNG), para 14.1, PDF p.1 (printed p.103), para 14.1
2016-08Shah Committee report (unjust enrichment; GoI entitled to restitution) Secondary sourcereported by Business Standard / Moneylife (IANS); primary not found
2018-07-24GoI claim for migrated gas; arbitral award in favour of consortium
~1.55 US$ billion (GoI claim)
Secondary source
RIL letter to BSE/NSE, "Update to disclosure dated February 15, 2025", para 1 (quoting 15 Feb 2025 disclosure)
2023-05-09Delhi HC single judge dismisses GoI challenge to awardRIL letter to BSE/NSE, 4 Mar 2025, para 1
2025-02-14Delhi HC Division Bench reverses single judge and sets aside awardRIL letter to BSE/NSE, 4 Mar 2025, para 1
2025-03-03MoPNG demand on PSC contractors after Division Bench judgment
2.81 US$ billion
RIL letter to BSE/NSE, 4 Mar 2025, paras 2-3
2025-2026Supreme Court appeals by RIL, BP, Niko against Division Bench judgment Secondary sourcereported by Deccan Chronicle, India Legal; primary not found

The auditor did not find that costs were inflated; it said it could not validate them. Separately, the arbitral award rejecting the government's gas-migration claim was set aside by the Delhi High Court in February 2025, and the petroleum ministry has demanded US$ 2.81 billion.

The documents

From CAG Reports No. 19 of 2011-12, No. 24 of 2014 and No. 11 of 2016, and Reliance's stock exchange filings of February and March 2025 on the court outcome and the demand. The Justice A.P. Shah committee report was not retrieved.

Every figure above is in the data tables with its source and page. Read the argument in full in Part 2 of the paper.